Stage 14 of 14High concentrationModerately hard to substitute
Chapter 14: Data Centers and Power
SemiAnalysis forecast in October 2026 that 50 GW of data center capacity would be added in 2027, about as much as the world had built through 2024. The large transformers that connect such sites to the grid commonly took three years to arrive in 2024.
Sharma, Yashvardhan. “Data Centers and Power.” Chip Supply Chain: How AI Chips Are Made. Updated 29 October 2026. https://chipsupplychain.org/data-centers-and-power/
A liquid-cooled rack of 72 GPUs, Nvidia’s GB200 NVL72, drawn to scale. It is 2.24 m tall and 600 mm wide, taller than a door. It weighs about 1.36 metric tons, more than a small car, and draws about 120 kW. The newer GB300 NVL72 draws up to 142 kW. The gray steel power shelves and the copper busbar they feed are picked out.
In plain terms
A data center feeds electricity to the machines inside it and carries away the heat they give off. One of AI , a cabinet taller than a door, can draw 142 1. Every watt of it comes back out as heat, and liquid piped through the rack carries the heat away1. A large training site already holds more than a hundred thousand chips2. The newest sites are planned in gigawatts3. One gigawatt is the whole output of a large power station, and Epoch AI projects that OpenAI’s seven Stargate sites in the United States will add up to more than nine of them by 20293. Getting that much electricity to the site is harder than putting up the building. and heavy switches connect a site to the grid, and turbines make the power. All of them come from a few suppliers and take years to arrive.
In short
Measured by capacity, US factories supplied 29.2 percent of the bought in the US in 2023, and imports the rest4. GE Vernova’s gas equipment backlog and reserved factory slots stood at 116 in mid-2026, against planned output of 20 GW a year from the third quarter5.
ERCOT, the grid operator for most of Texas, counted 9,456 MW of big power users approved to energize in its overview for September 20266. Judging by peak monthly use in September, it believed 4,132 MW of that was operating6. On 3 August 2026 Governor Greg Abbott ordered an audit of every data center seeking a connection before any data center project moves forward7. In September 2026 ERCOT said it had paused approvals to energize data centers of 75 MW or more until the audit and a review of their impact on local communities are complete8.
A passes through a in months, but in 2024 a commonly took three years to arrive9. Before the pandemic, the same order took under a year10.
- Who leads
- USGE Vernova Gas equipment, transformers and switchgear, including through Prolec GE13
- CHHitachi Energy Power transformers and switchgear13
- DESiemens Energy Grid technologies, transformers, turbines13
- JPMitsubishi Power Power generation equipment, including gas turbines13
- USVertiv Data center power systems11
- FRSchneider Electric Cooling, through its Motivair division14
- Where it is made
- USUnited States The largest data center operators, and GE Vernova turbines and grid equipment
- CHSwitzerland Hitachi Energy transformers and switchgear, and ABB switchgear
- DEGermany Siemens Energy grid technologies and turbines
- JPJapan Mitsubishi Power equipment, including gas turbines
- Why substitution is possible
- Buyers of grid equipment can choose among suppliers, and GE Vernova’s 2025 annual report names Hitachi Energy, Siemens Energy, Schneider Electric and ABB among its key competitors13. But in the United States in 2024 the longest reached 60 months9. An International Energy Agency survey published in 2025 found waits of up to four years worldwide15.
How AI data centers are powered and cooled
Power in, heat out

- The site. Data centers are where AI chips go to work. A large training site holds a hundred thousand of them, in rows of racks.
- Power in. Power comes in from the grid, stepped down by a substation, and runs through the data center to every rack. One rack of AI chips can draw 142 kilowatts.
- Heat. Every watt of it comes back out as heat, more than air can carry away.
- Water out. So water runs through plates on the chips, carries the heat to coolers outdoors and comes back. Nvidia plans for racks of a megawatt each from 2027, so the power coming in and the heat going out keep growing.
The is the basic unit of AI compute. Nvidia’s rack draws up to 142 through eight 33 kW , the rack’s own power supplies1. Large sites hold many such racks. Colossus 1, an AI data center in Memphis, Tennessee, held an estimated 230,000 Nvidia by July 20252.
Power reaches the rack through a chain of heavy equipment, and each piece has its own , the wait between order and delivery. Between the grid and the rack, a substation steps the high voltage down with transformers. Switchgear, the building’s heavy circuit breakers, can cut any part of the site off in a fault. Battery-backed supplies keep the racks running for the seconds it takes backup generators to start. Distribution boards split the feed among the rows of racks.
At the back of each rack, a carries the current down to the server trays. It is a solid copper bar, because an ordinary cable would overheat at that current.
Heat leaves in water. , metal blocks with coolant running through them, sit on the GPU packages and pass the heat to the building’s water loop, which releases it outdoors14. Nvidia’s Rubin racks run coolant at up to 45 °C, warm enough that in many climates the loop can release its heat without turning on chillers, the refrigeration machines that cool water14.
Nvidia is also moving the power that feeds its racks to 800 volts of direct current. Raising the voltage cuts the current needed for the same power, and the heat in copper comes from current. Nvidia said in October 2025 that at 800 volts the same wire can carry 157 percent more power than at 415 volts of alternating current20. Inside racks such as the GB300 NVL72, power runs at 54 volts, and at that voltage a one-megawatt rack would need up to 200 kg of copper busbar21.
Cooling and power options
Cooling
- Air. Heat exchangers in the rack door work when density, the power each rack draws, is moderate, but Nvidia’s GB300 NVL72 rack is liquid cooled1.
- Direct-to-chip liquid. Nvidia’s Rubin platform is 100 percent liquid cooled, and Nvidia says every cloud provider and data center operator building for it is moving to liquid14.
- Immersion. The servers sit in a bath of fluid, which makes them hard to service.
Nvidia says the cooling supply chain is keeping pace with the move to liquid14. Motivair, Schneider Electric’s cooling division, has worked with Nvidia for nearly a decade, following Nvidia’s product roadmap14.
Rack power
Nvidia’s 800-volt DC architecture is designed for racks from 100 kW to more than a megawatt, with megawatt racks from 202721. Nvidia is making the change because the 54-volt distribution in existing racks begins to hit physical limits once racks exceed 200 kW21.
Nvidia names nine data center power system providers for its 800-volt designs for gigawatt-scale data centers, among them ABB, Eaton, Hitachi Energy, Mitsubishi Electric, Schneider Electric, Siemens and Vertiv11.
A megawatt rack changes the busbar, the floor loading, the coolant flow, the leak detection and the energy stored in the rack. Nvidia’s Vera Rubin NVL72 rack design adds energy storage to keep power steady11.
Where the electrons come from
- Grid interconnection. The slow path in the United States, where the queues to connect are long3.
- Behind-the-meter gas, generation on the site itself. The fast path, which at least three of OpenAI’s seven US Stargate sites will use to avoid grid queues3.
- Nuclear. Existing plants already sell power to data centers22. Talen Energy supplies Amazon’s data center campus next to the Susquehanna nuclear plant in Pennsylvania under a June 2025 contract expected to reach 1,920 MW no later than 203222. Restarts and new reactors are still to come. Constellation signed a power purchase agreement with Microsoft to restart Three Mile Island Unit 1 as the 835 MW Crane Clean Energy Center19. The plant shut in 201923. A $1 billion federal loan that closed in November 2025 partly finances its restart, which is subject to licensing approvals from the US Nuclear Regulatory Commission23.
Data center spending and power equipment makers
The largest data center operators pay for the buildout. by Alphabet, Amazon, Meta, Microsoft and Oracle came to $448.2 billion in 2025, the sum of quarterly figures compiled by Epoch AI, a research group24. If the trend continues, it will reach $770 billion in 202624. The International Energy Agency expected worldwide investment in data centers to reach $580 billion in 202512.
Amazon spent the most of five large operators, $134.7 billion in 2025
Capital spending by five large US data center operators, 2025
| Amazon | $134.7B |
|---|---|
| Microsoft | $108.3B |
| Alphabet | $93.1B |
| Meta | $72.5B |
| Oracle | $39.6B |
Sharma, Yashvardhan. “Figure 14.2: Capital spending by five large US data center operators, 2025.” Chip Supply Chain: How AI Chips Are Made. Updated 29 October 2026. https://chipsupplychain.org/data-centers-and-power/#fig-data-centers-and-power-hyperscaler-capex. Data: Epoch AI, hyperscaler capex trend, February 2026, quarterly figures from company filings summed for 2025.
Epoch AI also projects that OpenAI’s seven US Stargate sites will exceed 9 GW by 20293. It expects the site in Abilene, Texas, to grow from an estimated 0.3 GW in April 2026 to 1.2 GW in the fourth quarter of 20263.
A few large firms make the turbines, transformers and switchgear. GE Vernova builds large gas turbines, and its 2025 annual report names Siemens Energy and Mitsubishi Power among the key competitors of its power generation business13. Its electrification business makes power transformers and switchgear, and the report names Hitachi Energy, Siemens Energy, Schneider Electric and ABB among that business’s key competitors13.
Equipment makers limit how fast the buildout can go. GE Vernova’s gas equipment backlog and reserved factory slots grew from 100 GW to 116 GW in the second quarter of 20265. In the first half of 2026, data center orders for its electrification business, which makes grid equipment, passed $5 billion, more than double that business’s data center orders for all of 20255. GE Vernova bought the remaining half of Prolec GE, a transformer maker, in the first half of 20265.
GE Vernova plans 30 GW of annual gas turbine output in 2030
GE Vernova’s planned annual gas turbine output
| Q3 2026 | 20 GW/yr |
|---|---|
| 2028 | 24 GW/yr |
| 2030 | 30 GW/yr |
Sharma, Yashvardhan. “Figure 14.3: GE Vernova’s planned annual gas turbine output.” Chip Supply Chain: How AI Chips Are Made. Updated 29 October 2026. https://chipsupplychain.org/data-centers-and-power/#fig-data-centers-and-power-turbine-output. Data: GE Vernova second-quarter 2026 results, July 2026.
Data center electricity demand forecasts
US data center electricity use is projected to rise steeply by 2030. US data centers used 192 in 2024, 4.7 percent of national electricity, according to a June 2026 estimate by Lawrence Berkeley National Laboratory that leaves out cryptocurrency mining25. The lab’s reference case, its main scenario, projects 464 TWh in 2028 and 649 TWh in 2030, which would be 11.8 percent of forecast US electricity use25. Its scenarios for 2030 range from 521 to 843 TWh, or 9.5 percent to 15.3 percent26.
The US Energy Information Administration expects electricity demand to keep rising, but in September 2026 it cut its 2027 forecast for the region that includes Texas. In its October 2026 Short-Term Energy Outlook, it expects US electricity sales of 4,152.0 TWh in 2026 and 4,216.6 TWh in 202727. It expects electricity demand from the commercial sector, which includes data centers, to grow 2.8 percent in 2027 and demand from industry to grow 2.7 percent28. Its September outlook had lowered the 2027 electricity sales forecast for the region that includes Texas by 4.7 percent from August29. That outlook noted that Texas had paused connecting new data centers to the grid while the state audits proposed projects30. The pause, set by the grid operator for most of Texas, covers data centers and crypto mining sites of 75 MW or more8.
US data centers’ projected 2030 use ranges from 521 to 843 TWh
US data center electricity use, 2024 and 2030 projection range
| 2024 | 192 TWh |
|---|---|
| 2030 low case | 521 TWh |
| 2030 reference case | 649 TWh |
| 2030 high case | 843 TWh |
Sharma, Yashvardhan. “Figure 14.4: US data center electricity use, 2024 and 2030 projection range.” Chip Supply Chain: How AI Chips Are Made. Updated 29 October 2026. https://chipsupplychain.org/data-centers-and-power/#fig-data-centers-and-power-us-dc-electricity. Data: Lawrence Berkeley National Laboratory, June 2026.
By the International Energy Agency’s estimate, China accounted for 25 percent of the world’s data center electricity use in 2024, second to the United States at 45 percent16. Data centers made up around 3 percent of the growth in China’s electricity demand from 2022 to 2024, the agency found17.
SemiAnalysis, a research firm, forecast in October 2026 that 50 GW of data center capacity would be added in 2027, which it said was about as much as the world’s data center market had built in total through 202431. Just 40 campuses in an advanced stage of construction held more than 24 GW, most of it to be delivered in 2027, it found31.
Better do not by themselves cut total energy use. Google says its Ironwood , an AI chip, delivers twice the performance per watt of Trillium, the TPU before it32. A token is the chunk of text a model reads or writes. Energy per token can fall while total energy use still rises, if the number of tokens rises faster.
Long waits for grid power and equipment
On the Texas grid, big power users have asked for far more electricity than is connected and running. ERCOT, the grid operator for most of Texas, was tracking about 474 GW of large loads (big power users) seeking a connection in June 2026, roughly 90 percent of it data centers33. In its operational overview for September 2026, ERCOT counted 9,456 MW of large loads approved to energize, that is, cleared to switch on6. Judging by peak monthly use in September, it believed only 4,132 MW of it was operating6.
Before a big user can connect, engineers must study whether the nearby grid can carry its load. In a preliminary review in July 2026, ERCOT found that about 205 GW of the requests already had such a study, which made them eligible for Batch Zero, the first batch of requests it studies together34. In September 2026 ERCOT conditionally classed 66.4 GW of Batch Zero projects as base load and 127.9 GW as studied load, pending final decisions in December8. Under ERCOT’s Batch Zero rules, base load is demand from projects already running or far enough along to be counted without further study35. Studied load is demand that ERCOT will study before giving each project a share of the grid’s capacity35.
Texas has paused new connections for large data centers while it audits them. On 3 August 2026 Texas Governor Greg Abbott ordered the state’s Public Utility Commission and ERCOT to audit every data center waiting to connect to the grid before any data center project moves forward7. ERCOT then paused approvals to energize data centers and crypto mining sites of 75 MW or more until the audit and a review of their impact on local communities are complete8. It will report on the audit and the community review to the Public Utility Commission by 10 December 20268.
Projects in that queue also wait on equipment.
- Large power transformers. In the United States in 2024, lead times of 36 months were commonly quoted and the longest reached 60 months, against under a year before the pandemic9. By a US Commerce Department estimate, 82 percent of the units put into US service in 2019 were imported36. In an industry survey published in 2025, the International Energy Agency found that large power transformers took up to four years to secure worldwide15. It also found that their average lead times had almost doubled since 202115. A transformer’s size is given as a power rating in megavolt-amperes (MVA)9. Measured by capacity, US factories supplied 29.2 percent of the transformers rated 60 MVA and above bought in the US in 2023, and imports supplied the rest4.
- Gas turbines. GE Vernova’s gas equipment backlog and reserved factory slots stood at 116 GW in mid-20265. In July 2026 it expected to build gas turbines at a yearly rate of 20 GW in the third quarter of 2026, 24 GW in 2028 and 30 GW in 20305.
- Firm generation, the kind that runs whatever the weather. The Nuclear Regulatory Commission has approved a fuel license amendment for the Crane plant18. Constellation called the approval a major milestone toward restarting the plant in 202718.
Memory chips are also in short supply. Micron’s quarterly report for the period ended 28 May 2026 says AI-driven growth in demand for memory and storage is outpacing industry supply37. The memory shortage and the wait for power equipment both limit how much of the 2026 capital spending turns into working compute.
Flashcards
Recall each answer, then turn the card.
What does a data center do for AI chips?
It feeds them electricity and carries away the heat they give off.
Why are AI racks cooled with liquid?
One rack can draw 142 kilowatts, and every watt comes back out as heat.
How big are the newest AI data centers?
They are planned in gigawatts, and each gigawatt is the output of a large power station.
What slows down building an AI data center?
The power equipment. Transformers and turbines come from a few suppliers and take years to arrive.
Four things to remember
- One AI rack can draw 142 kilowatts, too much heat for air, so racks are cooled with liquid.
- The newest AI sites are planned in gigawatts, and each gigawatt is the output of a large power station.
- Power equipment is one of the slow parts of building a data center. In 2024 lead times of 36 months were commonly quoted for a large transformer.
- The United States used 45 percent of the world’s data center electricity in 2024 and China 25 percent, by the International Energy Agency’s estimate.
Sources (37)
Source tiers A company filings, governments, standards bodies, universities and research institutions. B SemiAnalysis, Reuters, the Financial Times and Nikkei Asia.
- ASystem Hardware & Components
- AColossus 1, AI data centers directory
- AOpenAI Stargate: where the US sites stand
- ALarge Power Transformers from South Korea, Investigation No. 731-TA-1189 (Second Review), Publication 5531
- AGE Vernova, current report on Form 8-K dated 22 July 2026
- AElectric Reliability Council of Texas, ERCOT Monthly Operational Overview (September 2026)
- AGovernor Abbott Directs Comprehensive Data Center Audit
- AElectric Reliability Council of Texas, Item 14: Batch Zero Update, Board of Directors meeting, 14-15 September 2026
- AU.S. Department of Energy Large Power Transformer Resilience Report to Congress, July 2024
- AU.S. Department of Energy Large Power Transformer Resilience Report to Congress, July 2024
- ANVIDIA, Partners Drive Next-Gen Efficient Gigawatt AI Factories in Buildup for Vera Rubin
- AExecutive summary – World Energy Outlook 2025
- AGE Vernova, annual report on Form 10-K for the fiscal year ended 31 December 2025
- AHotter Than a Hot Tub: The 45°C Breakthrough to Cool AI’s Biggest Machines
- AExecutive summary – Building the Future Transmission Grid
- AExecutive summary – Energy and AI
- AExecutive summary – Electricity 2025
- AConstellation Reports Second Quarter 2026 Results
- AConstellation Ahead of Schedule for Launch of Crane Clean Energy Center
- ABuilding the 800 VDC Ecosystem for Efficient, Scalable AI Factories
- ANVIDIA 800 VDC Architecture Will Power the Next Generation of AI Factories
- ATalen Energy, current report on Form 8-K dated 11 June 2025
- AEnergy Department Closes Loan to Restart Nuclear Power Plant in Pennsylvania
- AHyperscaler capex has quadrupled since GPT-4’s release
- AUnited States Data Center Energy Usage Report: 2025 Update
- AUnited States Data Center Energy Usage Report: 2025 Update
- AShort-Term Energy Outlook, October 2026
- AShort-Term Energy Outlook, October 2026
- AShort-Term Energy Outlook, September 2026
- AShort-Term Energy Outlook, September 2026
- BDatacenters 2027: The Year of Acceleration, +50GW in a Single Year
- AInside the Ironwood TPU codesigned AI stack
- AElectric Reliability Council of Texas, ERCOT update to the Senate Committee on Business and Commerce, 29 July 2026
- AElectric Reliability Council of Texas, ERCOT update to the Senate Committee on Business and Commerce, 29 July 2026
- Ahttps://www.ercot.com/mktrules/issues/PGRR145
- AU.S. Department of Energy Large Power Transformer Resilience Report to Congress, July 2024
- AMicron Technology, quarterly report on Form 10-Q for the quarter ended 28 May 2026